One of the largest new business centres in Belgrade
» Investor
Wiener Städische and Promo Media, Investition worth - 50 mil €
» Location
Blok 11a, New Belgrade
» Size
21 000 square metres of rentable modern office space
» Deadlines
Construction started in June 2008, finishing it is planed for Summer 2010
Visualisation of the object
Updated on June 06, 2008
Updated on June 19, 2008
Updated on October 5th, 2008
Updated on October 27th, 2008
Updated on December 3th, 2008
Updated on January 5th, 2009
Updated on March 14th, 2009
Updated on April 11th, 2009
Updated on July 13th, 2009
Updated on November 4th, 2009
Updated on December 18th, 2009
Updated on March 1st, 2010
Log - June 02 2008
Ground Works on the construction site, tennis training area was demolished, machinery is digging a big hole.
Log - June 06 2008
Big foundation hole seen.
Log - June 15 2008
"Wiener Städische" invests 50 mil. € in this project.
Log - October 05 2008
First floors now under construction
Other news
27 Jul 2010Ada Bridge - Exclusive photo report 07 Jul 2010"Gazela" Bridge - Reconstruction report 01 Jul 2010Plans for Block 65 Development 29 Jun 2010First retail center in Kaludjerica 23 Jun 2010Construction Updates - June 2010 19 Jun 2010Radnicka Street Intersection - plan overview 16 Jun 2010New LED street lights in Belgrade